June 23, 2020
Completed Works: Clearing completed from Sta 65+00 to 73+45 as scheduled. An additional SRG Crew will be starting this week to follow and tidy-up the brushing of the previously cleared areas. There is also another Falling Crew that will start to help accelerate the clearing. There is one Traffic Control Crew and we have added an additional member to that crew to utilize more of the local resources. There will be an added crew the week of June 29th to July 3rd. Planned shut down for the 3rd of July, in lieu of Canada Day.
Environmental: Environmental crews have been busy providing support with bird nest sweeps ahead of construction crews, and have included two local members. Several nests were identified and protected with no-work buffers. Additional to survey crews, a full time environmental monitor is providing ongoing support to construction activities. No environmental concerns have arisen as a result of construction activities.
Brittany Simpson SRG Project Liasion
15LS0646 COMPILED LOT 64
15LS0646 COMPILED LOT 67
15LS0646 COMPILED LOT 73
15LS0646 COMPILED LOT 77 242
download the road survey plans...
Like Us on Facebook
Office Location: 7555 Dunn Lake Road, B.C Office Hours: 8:00am-4:00pm Monday to Friday
Phone: 250.672.9995 Toll-Free: 1.800.678.1129 Fax: 250.672.5858 Email: reception@simpcw.com